Its day 9 of the renovation.
*There is a blur spot in all the photos due to my dirty lens.*
- This is the 6th day of tiling works.
- The sand, tiles and cement in the living room are almost used up.
- Protective sheets are laid to protect the installed new living room tiles from damages.
- Tiling works for a normal HDB flat or condo apartment takes about 7 working days to complete.
- The kitchen wall is cement screeded.
- Mortar base is build for the kitchen cabinet, washing machine and refrigerator. The reason for build the base is to prevent any water from damaging the cabinet or electronics while cleaning or washing the kitchen floor.
- Partial tiling works for the common toilet is done.
- Because the opening for the toilet door is too big (after hacking away the old tiles), hollow blocks and cement are used to fix up the area to standard door size.
- Nothing is done to the princess room yet.
- Nothing is done to the study room too.
- Nothing is done to the master room as well.
- Partial tiling works is done for the master toilet.
Information about the Interior Designer:
Name: Ben Ng
Experiences: working as a Interior Designer since 2006
Mobile: 9746 2581
Company: BEHome Design Concept
Website: http://www.behomedc.com/index.htm
Do mention Vincent Interior Blog for special discount or free gift! No commission is given to Vincent Interior Blog (promise, swear and guarantee!), so you can be assured that you get the best pricing for your renovation!