Punggol 4 Room HDB Renovation: Part 5 – Day 14

On day 14 of the renovation, all tiling works are completed!

Living Room

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Living Room 1

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Living Room 2

  • After clearing off all the debris, the house is ready for the rest of the renovation works: carpentry, electrical works, sanitary installation, painting, etc.
  • Protective sheets are laid over the new tiles.

Kitchen

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Kitchen 1

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Kitchen 2

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Kitchen 3

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Kitchen 4

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Kitchen 5

  • The kitchen wall is plastered smooth.
  • Motar base is completed.
  • More electrical works done: wiring and switches are installed.
  • Loose wires will be connected once the carpentry are installed.
  • At this stage, the carpentry will be able to take accurate measurement of the space for the kitchen cabinets and spray painted tempered glass backing.

Common Toilet

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Common Toilet 1

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Common Toilet 2

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Common Toilet 3

  • The common toilet is ready for other installation works: toilet bowl, sink, tap, water tank and shower installation.
  • Toilet door is also ready for measurement and installation.

Common and Master Rooms

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Common Room 1

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Common Room 2

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Master Room 1

  • The rooms are waiting for flooring works, painting, doors installation, air conditioning and electrical works.
  • The master room is also waiting for carpentry  measurement and installation.

Master Toilet

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Master Toilet 1

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Master Toilet 2

Punggol 4 Room HDB Day 14 ( Tiling Works Completed)-Master Toilet 3

  • There are more items to install as compared to the common toilet.
  • There is a shower screen and a vanity cabinet to be installed.

Information about the Interior Designer:

Interior Designer Ben Ng

Name: Ben Ng

Experiences: working as a Interior Designer since 2006

Mobile: 9746 2581

Company: BEHome Design Concept

Website: http://www.behomedc.com/index.htm

Do mention Vincent Interior Blog for special discount or free gift! No commission is given to Vincent Interior Blog (promise, swear and guarantee!), so you can be assured that you get the best pricing for your renovation!


Blog about Interior Design, renovation and home improvement.

Advertisement

No comments.

Leave a Reply

%d bloggers like this: