A normal full renovation like this 4 room HDB takes about 6 weeks to complete. As we approach the end of week 4, all the major works are about to be completed.
Living Room
- The front door and gate were repainted.
- Carpentry works: A divider with shelvings and a TV console were installed.
- Sanitary and kitchen accessories were delivered and placed in the living room.
Kitchen
- The kitchen cabinet is still in “work in progress” stage.
- The hood and hob were installed.
- The “unsightly” pipe will be concealed by the carpentry works.
Common Toilet
- After some cleaning up, the beautiful tiling works can be seen clearly.
Common Room 1
- The white background with pink strips creates a lovely ambience for the princess room.
- Vinyl flooring was installed.
- 3 inch timber skirting is used for the whole house.
Common Room 2
- Painting and flooring works were completed.
- The old door frames were repainted.
Master Room
- The carpenter is doing the final touch up of the custom made wardrobe.
- Blum hinge system is used to ensure the doors are closed silently and effortlessly. Blum is the leading brand that provides accessories for furnitures and cabinets makers.
Master Toilet

Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Toilet – Vanity Punggol 4 Room HDB Day 25 (Carpentry Works) – Master Toilet – Vanity
Information about the Interior Designer:
Name: Ben Ng
Experiences: working as a Interior Designer since 2006
Mobile: 9746 2581
Company: BEHome Design Concept
Website: http://www.behomedc.com/index.htm
Also see here for another of his master piece.
Do mentioned that you viewed his works on Vincent Interior Blog for attractive discounts or free gifts!