Punggol 4 Room HDB Renovation: Part 7 – Day 29 – Carpentry Works

Its been a month now.  All renovation works are rushing to meet the deadline.  Its really not an easy job to coordinate so many parties and works at the same time.  Thats why being well organised is very important to a Interior Designer.

Living Room

Punggol 4 Room HDB Day 29 (Carpentry Works)-Living Room 1

Punggol 4 Room HDB Day 29 (Carpentry Works)-Living Room 2

Punggol 4 Room HDB Day 29 (Carpentry Works)-Living Room 3

Punggol 4 Room HDB Day 29 (Carpentry Works)-Living Room 4

  • The electrician cuts holes on the false ceiling to install the down lights.

Kitchen

Punggol 4 Room HDB Day 29 (Carpentry Works)-Kitchen 1

Punggol 4 Room HDB Day 29 (Carpentry Works)-Kitchen 2

Punggol 4 Room HDB Day 29 (Carpentry Works)-Kitchen 3

Punggol 4 Room HDB Day 29 (Carpentry Works)-Kitchen 4

Punggol 4 Room HDB Day 29 (Carpentry Works)-Kitchen 5

  • The kitchen cabinet is almost completed.
  • Hob and hood are installed.
  • The loose wires sticking out from the kitchen cabinet are waiting to be connected.
  • Measurement for the spray painted tempered glass backing is completed.  Waiting for the glass to be manufactured and install.

Common Room

Punggol 4 Room HDB Day 29 (Carpentry Works)-Common Room 1

Punggol 4 Room HDB Day 29 (Carpentry Works)-Common Room 2

Punggol 4 Room HDB Day 29 (Carpentry Works)-Common Room 3

  • Lightings were installed.
  • I really like the flower-designed ceiling light from Chan Huat.  It cost about SGD$300 plus before discount.  It really matches the princess room!
  • Veneer doors are also installed in all rooms.

Master Room

Punggol 4 Room HDB Day 29 (Carpentry Works)-Master Room 1

Punggol 4 Room HDB Day 29 (Carpentry Works)-Master Room 2

  • The wardrobe is completed.
  • I really like the nice finishing.  Just look at the edge of the wardrobe door.  It just look straight and even.

Master Toilet

Punggol 4 Room HDB Day 29 (Carpentry Works)-Master Toilet 1

Punggol 4 Room HDB Day 29 (Carpentry Works)-Master Toilet 2

Punggol 4 Room HDB Day 29 (Carpentry Works)-Master Toilet 3

  • Lights are installed behind the carpentry works.
  • After the mirror and accessories are installed, it will look really impressive.

Common Toilet

Punggol 4 Room HDB Day 29 (Carpentry Works)-Common Toilet 1

Punggol 4 Room HDB Day 29 (Carpentry Works)-Common Toilet 2

Punggol 4 Room HDB Day 29 (Carpentry Works)-Common Toilet 3

  • This is the bi-fold door from Besglas.


Blog about Interior Design, renovation and home improvement.

Advertisement

One Response to “Punggol 4 Room HDB Renovation: Part 7 – Day 29 – Carpentry Works”

  1. Peter

    Oct 14. 2012

    Nice

    Reply to this comment

Leave a Reply

%d bloggers like this: